Back on Track

The contractor who has worked for us so far has become quite frazzled.  He has 4 building sites with 5 houses to finish but only 20 workers. No wonder can he keep neither deadlines nor quality standards. Workers are in high demand in Chiang Mai because there are so many building sites some of them huge. There is such a shortage that workers are recruited quite aggressively.

After a long construction delay we have decided to terminate this contractor and find a new one. We believe to have found a good solution with khun Youd and his team. They want to finish our house within an acceptable time frame. The deadline is now set to October 31, 2012. Khun Youd has been recommended to us and we have a very good impression of him.


On the day after the agreement there were already workers on site to prepare for the coming work processes. New material had to be ordered immediately and things are happing again at the building site.


 More and more workers will be arriving as the project they are working on still (the house of another foreigner) is nearly completed. The people for tiling, painting etc. will soon be available to us.  


We are relieved to see that the atmosphere at the site is good, work is in progress and the quality standards are higher.