Mittwoch, 5. Dezember 2012

The Guesthouse in finished

Finally. There is no running water yet, though. Apart from some details it is all ready now:

Samstag, 17. November 2012

Lots of pictures

Quite a lot has been going on. Just as well because actually we planned on moving in tomorrow. This won't be possible though as you will see in the pictures.

sanwash is used in several places
here they are making samples for us to choose from
work in progress

the contractors wife is working with him but does not want to get a tan

the spirit house gets a stronger pole

and the workers arriving for another day

the celing on the veranda

now the tiling can start here as well

taking a well deserved break

and tiling the carport

an overview middle of November

Montag, 12. November 2012

What a Rock

 After we decided to the landscaping ourselves, we went looking for other significant pieces of decoration. When we found this rock we immediately fell in love with it.


Two days later we had the granite rock delivered to the site.

Because the crane was too small, a larger one was called for.

Then, they were ready to go.

With 3600 kgs it is quite a rock.

The next ocstacle was the power lines which wer etoo low.

But that's no problem for an agile Thai.

Making sure it faces the correct way.